Marrakesh Country Club Weekly Construction Progress Update, Week Ending July 30th, 2021:    

Rerouting of plumbing water and gas at new elevator area Continue rerouting of electrical conduits and plumbing lines around elevator Demo of service yard roof canopy Exterior stucco removal

Next Week’s Activities:    

Rerouting of plumbing water and gas at new elevator area Finish stucco removal at all storefronts Install new underground plumbing Finish demo of existing cart garage roofing