Marrakesh Country Club Weekly Construction Progress Update, Week Ending August 6th, 2021:     

Rerouting of plumbing water and gas at new elevator area Finish stucco removal at all storefronts Install new underground plumbing Finish demo of existing cart garage roofing Start wood framing new office 212

Next Week’s Activities:   

Rerouting of plumbing water and gas Finish rerouting of existing electrical conduits Begin excavating for new underground utilities