Marrakesh Country Club Weekly Construction Progress Update, Week Ending August 20th, 2021:    

Continue excavating for new underground utilities and footings Form and set rebar for new footings and elevator pit Continue rerouting plumbing and electrical Begin to install building shoring

Next Week’s Activities:   

Form and set rebar for new building footings Finish installing new underground plumbing at restrooms on bottom floor Continue to install building shoring at bottom floor

Progress Photos: