Marrakesh Country Club Weekly Construction Progress Update, Week Ending September 3rd, 2021:    

Continue excavating and setting rebar for new footings Demo concrete slab for underground electrical Reroute overhead water and gas at elevator area Demo existing CMU wall footing at the service yard

Next Week’s Activities:    

Demo remaining footings, bearing walls, and wood posts Reroute existing underground electrical at fitness room Inspect and pour footings and elevator pit Set column base footing templates