Marrakesh Country Club Weekly Construction Progress Update, Week Ending September 17th, 2021:    

Reroute existing underground conduits in the fitness room Pour concrete for elevator pit and new wall footings on North side Installation of new c-channel steel on second floor dining area Set new steel columns on first floor

Next Week’s Activities:    

Layout and begin wood wall framing at North side addition Continue to set steel columns at first floor Finish installation of new c-channel steel on second floor Remove structural shoring from second floor glu-lam beam.

Progress Photos: