Marrakesh Country Club Construction Progress Update - December 17th 2021 This Weeks Activities * Rough in electrical conduits at ceiling and walls on first and second floor * Wood wall framing / truss blocking, install conduits to panel KS-1 * Excavate, form, and dowel rebar for concrete footings

Next Weeks Activities * Continue rough electrical conduits at ceiling and walls * Inspect and pour back slab trenches, floor patches, and footings * Lay out new kitchen hood roof equipment, MUA and EX fans Progress Photos:

R.C. Construction Services, Inc | 2223 N. Locust Ave Rialto CA 92377 909-829-3688 ph | 909-829-3696 fax | License # 716719 www.rcconstruction.com