AGENDA AGENDA
1. Project Introduction 2. HSE improvement plan & key highlights 3. QA/QC improvement plan & key highlights 4. Monthly project progress update 5. Resource planning 6. Post Covid’19 Challenges 7. SMART Construction & HILTI Update 8. New Ideas /System 9. Project Finance status 10.Satellite Support Team 11.Save & share implementation
Project Introduction Project Summary Project Name
MELAKA 2,242MW CCGT POWER PLANT PROJECT
Location
Melaka, Malaysia
Client
Hyundai Engineering (M) Sdn Bhd Electrical & Instrumentation Works
Control Board & Monitoring System Installation
DCS & PLC System Installation
Local Control Panel / Junction Box Installation
Impulse Line Piping & Tubing Works
Summary Scope of Work
Project Duration
3 March 2021
Conduit & Tray Installation Cabling Works
Field Instrument Installation
Calibration of Instruments
Support fabrication
Testing (Leak test) & Checking (Loop Check)
Commissioning assistance
Project Schedule 23 months Start : May 2019 Completion : May 2021 Strictly Confidential
3
Project Introduction 100% 100% Wastewater Treatment Area(WWTP)
95%
Unit 01 Heat Recovery Steam Generator(HRSG), Turbine bldg (GT&ST) and BOP
Unit 02 Heat Recovery Steam Generator(HRSG), Turbine bldg (GT&ST) and BOP
100% FUEL OIL UNLOADING/LOA DING AREA
100% Air Comp. System
100% Aux Boiler Area
100% Intake Facilities & ECS system
85% Unit 03 Heat Recovery Steam Generator(HRSG), Turbine bldg (GT&ST) and BOP
100% 100%
Workshop Building
Fuel Gas Supply System & Fuel Gas Compressor area Administration & Control Bldg
100% 3 March 2021
LEGEND:
C&I Work Completed
Black Start Diesel Generator Area
100%
C&I Work Under Progress
Strictly Confidential
4
Project Introduction UNIT -02 (BALANCE MODFIFCATION ACTIVITY UPON SBO CARRY OUT)
Strictly Confidential
Project Introduction UNIT -03 (BALANCE WORK GT & ST AREA
Strictly Confidential
Project Introduction Balance of Work Schedule
S.NO 1 2 3
AREA UNIT-02 UNIT-03 Pre-com activities
Jan-21
Feb-21
Mar-21
Owner keep on providing the additional works in Unit #02 & Unit #03
Strictly Confidential
Project Introduction Punch List Summary
AREA PUNCH ACTION UNIT TOTAL REMARKS CATEGORY BY COMMON UNIT-01 UNIT-02 UNIT-03 CAT “C”
No’s
85
59
148
160
452
HEM
CAT “C
No’s
9
125
138
182
454
GE
CAT “C
No’s
0
0
59
219
278
RMEC
1184 CAT “A” & “B’ Punches are closed, above mentioned Open Punches are “C” category only and all the punches related to plant operation to be close accordingly. Strictly Confidential
Project Introduction MAJOR ACTIVITIES UNIT#1 Operation started running continuously. UNIT#2 SBO modification works ongoing 2nd steam blow out planned on next month UNIT#3 Minor GT Instrument Installation works ST area cabling & termination works Loop Check ongoing OTHERS Commissioning Manpower(21 pax) assistance expected to be extend until end of June 2021 Ongoing additional works from HEM/GE due to design changes during operation period Discussion ongoing with Edra to Register RotaryMec as a Subcon for Maintenance works. Strictly Confidential
Project Introduction MAJOR ACTIVITIES UNIT#1 Operation started running continuously. UNIT#2 SBO modification works ongoing 2nd steam blow out planned on next month UNIT#3 Minor GT Instrument Installation works ST area cabling & termination works Loop Check ongoing OTHERS Commissioning Manpower(21 pax) assistance expected to be extend until end of June 2021 Ongoing additional works from HEM/GE due to design changes during operation period Discussion ongoing with Edra to Register RotaryMec as a Subcon for Maintenance works. Strictly Confidential
AGENDA AGENDA
1. Project Introduction 2. HSE improvement plan & key highlights 3. QA/QC improvement plan & key highlights 4. Monthly project progress update 5. Resource planning 6. Post Covid’19 Challenges 7. SMART Construction & HILTI Update 8. New Ideas /System 9. Project Finance status 10.Satellite Support Team 11.Save & share implementation
HSE IMPROVEMENT PLAN & KEY HIGHLIGHTS Safety Manhours 24,792
833,773
Man-hours for
Cumulative Man-hours
Jan 2021
Jan 2021
HSE Lagging Indicators of Jan 2021
Fatality
0(0) Fire (Minor)
0(0)
Lost Time Incident (LTI)
Restricted WorkDay Case (RWC)
0(0)
0(0)
Environment Spill (Minor)
First Aid Case (FAC)
0(0)
2(0)
Medical Treatment Case (MTC)
0(0) Regulatory noncompliance (Fines
Near Miss
1(0) Vehicle Incident
/ Summons)
0(0)
0(0) Strictly Confidential
HSE IMPROVEMENT PLAN & KEY HIGHLIGHTS Leading Indicators As of 31st Jan 2021
LEADING INDICATOR
UNIT
MONTHLY TARGET
THIS MONTH
PROJECT TO DATE
Safety Observation (UAUC)
Nos
105
113
2911
HSE Training Manhours
Hrs
660
723
723
HSE Management Walkabout
Nos
2
1
30
Toolbox Talk
Nos
31
30
558
HSE Weekly Meeting
Nos
2
1
45 Strictly Confidential
HSE IMPROVEMENT PLAN & KEY HIGHLIGHTS UAUC SUMMARY 6 5 3
3 3 2 2
2
3 2
2
2
1
Poor Practice
Good Observation
PPE : Not wear safety goggles. Access, WAH, Electrical and Confined Space : Mostly work area are have good improvement during safety do inspection. Strictly Confidential
HSE IMPROVEMENT PLAN & KEY HIGHLIGHTS Observation:
- Mostly people didn’t wear safety glass (Not comply Life Saving Rules (LSR 11) agreement number 2)
Investigation:
- People complaint have foam at safety glass when do the work because of face mask. - Safety glass missing
Action:
- Give awareness (Toolbox Safety Briefing) safety glass and why we need wear and effect when ignore LSR 11. - Inform to logistic pass new safety glass to supervisor and pass to their teammates.
Strictly Confidential
HSE IMPROVEMENT PLAN & KEY HIGHLIGHTS Safety Google Awareness Training
Strictly Confidential
HSE IMPROVEMENT PLAN & KEY HIGHLIGHTS Observation:
- Some of group didn’t do housekeeping and left unused materials at work area.
Investigation:
- Other discipline subcontractor also working the same location. - Unused materials was not barricade
Action:
- Remind to supervisor and workers effect of poor housekeeping (slip and falls) - Do practice before and after work do housekeeping
Strictly Confidential
HSE IMPROVEMENT PLAN & KEY HIGHLIGHTS Housekeeping Awareness Training
Strictly Confidential
HSE IMPROVEMENT PLAN & KEY HIGHLIGHTS Training Schedule
Strictly Confidential
HSE IMPROVEMENT PLAN & KEY HIGHLIGHTS Tools & Equipment Inspection
Strictly Confidential
HSE IMPROVEMENT PLAN & KEY HIGHLIGHTS Walkabout
Strictly Confidential
HSE IMPROVEMENT PLAN & KEY HIGHLIGHTS Training Manhours for 2021
Description
Manhours Percentage
Cum. Plan Training Hrs as of Jan’2021
Cum. Actual Training Hrs as of Jan’2021
Plan Training Hrs of Jan’2021
Actual Training Hrs of Jan’2021
660
723
660
723
109.54%
109.54%
MMCC Project Training Details for Jan'20Strictly Confidential
HSE IMPROVEMENT PLAN & KEY HIGHLIGHTS Training Manhours for 2020 Description Manhours
Cum. Plan Training Hrs as of Dec’2020
Cum. Actual Training Hrs as of Dec’2020
Plan Training Hrs of Dec’2020
Actual Training Hrs of Dec’2020
15,487
25,462
870
848
Percentage
164.41%
97.47%
Training Manhours for 2019 Description Manhours Percentage
Cum. Plan Training Hrs as of Dec’2019
Cum. Actual Training Hrs as of Dec’2019
7,506
7,601 101.26%
MMCC Project MMCC Project Training Details of 201 Training Details for Dec'20
Strictly Confidential
AGENDA AGENDA 1. Project Introduction 2. HSE Improvement Plan & Key Highlights 3. QA/QC Improvement Plan & Key Highlights 4. Monthly Project Progress Update 5. Resource Planning 6. Post Covid’19 Challenges 7. SMART Construction & HILTI Update 8. New Ideas /System 9. Project Finance Status 10.Satellite Support Team 11.Save & Share Implementation
QA/QC IMPROVEMENT PLAN & KEY HIGHLIGHTS
S/N 1 2 3 4 5 6 7
Description Total Estimated Request for Inspection (RFI) Total Raised Request for Inspection (RFI) Cancelled Request for Inspection (RFI) Last Month Request for Inspection (RFI) RFIOpen* by HEM(Client) RFI Open* by Edra (Owner) Closed Request for Inspection (RFI) Reason for Open RFI’s
Inspection ongoing RFI Prepared & Submitted to HEM Total RFI Open
Discipline Inst INST Total Material 5000 4827 116 269 20 13 4678
0 0 0 0 0 0 0
5000 4827 116 269 20 13 4678
No of RFI’s
20 13 33 Strictly Confidential
QA/QC IMPROVEMENT PLAN & KEY HIGHLIGHTS QC SUMMARY
6000
5000
4827
4678
4000
3000
2000
1000
20
0 TOTAL RAISED RFFI
CLOSED RFI
RFIOPEN* BY HEM(CLIENT)
13
269
RFI OPEN* BY EDRA LAST MONTH RFI (OWNER)
116 CANCELLED RFI
Strictly Confidential
QA/QC IMPROVEMENT PLAN & KEY HIGHLIGHTS TOP SUMMARY(As OF END JAN’2021) 120
104
104
99
100
80
80
78
68
99
66
60 40 20
2
0
0 UNIT #1
UNIT #2 Total TOP
S/N 1 2 3 4
Description Unit #1 Unit #2 Unit #3 Common Total
UNIT #3 Completed TOP
Total TOP
104 80 97.5 % COMPLETED 97.0 % COMPLETED 68 100 % COMPLETED 99 98.8 % COMPLETED 351 100 % COMPLETED
2
0 COMMON
Balance TOP
Completed TOP
Balance TOP
104 78 66 99 347
0 2 2 0 4 Strictly Confidential
QA/QC IMPROVEMENT PLAN & KEY HIGHLIGHTS HEM LOOP CHECK STATUS(As OF END JAN’2021) 3063
1309
1309
1309
1309
1280
607
UNIT #1
UNIT #2 Total HEM Loop
1 2 3 4
702 46
29
0
S/N
3017
Description
UNIT #3 Completed HEM Loop
Total Loop
COMMON
Balance HEM Loop
Completed Loop Balance Loop
100 % COMPLETED
1309 1309 1309 3063
1309 1280 607 3017
29 702 46
89 % COMPLETED
6976
6213
777
Unit #1 Unit #2 Unit #3 Common
100 % COMPLETED
Total
98 % COMPLETED 47.0 % COMPLETED
Strictly Confidential
AGENDA AGENDA 1. Project Introduction 2. HSE Improvement Plan & Key Highlights 3. QA/QC Improvement Plan & Key Highlights 4. Monthly Project Progress Update 5. Resource Planning 6. Post Covid’19 Challenges 7. SMART Construction & HILTI Update 8. New Ideas /System 9. Project Finance Status 10.Satellite Support Team 11.Save & Share Implementation
Monthly project progress update Overall Instrumentation Construction Progress
11.50%
11.70%
11.50%
10.58%
6.50%
0.00%
3.60%
12.55%
12.70%
12.00%
6.80%
6.80%
5.40%
2.23%
0.00%
0.26%
0.21%
0.53%
0.81%
3.07%
3.80%
4.06%
7.05%
7.51%
5.69%
0.00%
3.63%
11.85%
13.20%
12.30%
6.70%
6.70%
5.60%
2.30%
1.55%
0.00%
0.07%
-0.09%
0.06%
-0.08%
1.29%
0.12%
-1.24%
0.02%
0.03%
0.09%
0.00%
0.03%
-0.70%
0.50%
0.30%
-0.10%
-0.10%
0.20%
0.07%
-0.45%
Cum Baseline Plan
0.00%
0.19%
0.49%
0.96%
1.85%
3.63%
7.31%
12.61%
19.64% 27.12%
37.42%
48.22%
59.72%
71.42%
82.92%
93.50%
100.00%
Cum. Forecast Plan
0.00%
0.19%
0.49%
0.96%
1.85%
3.63%
7.31%
12.61%
19.64% 27.12%
32.72%
32.72%
36.32%
48.87%
61.57%
73.57%
80.37%
87.17%
92.57%
94.80%
96.80%
0.00%
0.26%
1.00%
1.81%
4.88%
8.68%
12.74%
19.79% 27.30%
32.99%
32.99%
36.62%
48.47%
61.67%
73.97%
80.67%
87.37%
92.97%
95.27% 96.82%
0.15%
0.27%
0.27%
0.30%
-0.40%
0.10%
0.40%
0.30%
0.20%
0.40%
0.47%
0.47% -0.02%
0.04% -0.04% 1.25% 1.37% 0.13%
0.18%
Jan-21
Feb-21
Mar-21
Aug-20
Jul-20
Jun-20
May20
Sep-19
Jul-19 0.00% 0.07%
Mar-21
10.80%
5.60%
Feb-21
10.30%
7.48%
Cum Actual Diff.
Jan-21 Dec-20
7.48%
7.03%
Dec-20 Nov-20
Nov-20
7.03%
5.30%
Oct-20
Apr-20 May-20
Oct-20
Mar-20
5.30%
3.68%
Sep-20
Feb-20
3.68%
1.78%
Sep-20
Jan-20 Feb-20
1.78%
0.89%
Aug-20
Dec-19 Jan-20
0.89%
0.47%
Jul-20
Nov-19 Dec-19
0.47%
0.30%
Jun-20
Oct-19
Apr-20
Sep-19
0.30%
0.19%
Mar-20
Aug-19
Nov-19
Jul-19
0.19%
0.00%
Aug-19 Jun-19
0.00%
Jun-19
Baseline Plan Forecast Plan Actual Diff.
May-19
May19
Oct-19
120.00% 15.0% Baseline Plan Forecast Plan Actual Cum. Forecast Plan 12.55%Cum Actual 13.20% 14.0% 12.70% 12.30% 13.0% 12.00% 11.85% 11.70% 100.00% 11.50% 11.50% 96.80% 98.50% 100.00% 12.0% 94.80% 96.82% 87.17% 92.97% 10.80% 92.57% 95.27% 10.58% 10.30% 11.0% 87.37% 80.67% 80.37% 80.00% 10.0% 73.97% 73.57% 9.0% 7.48% 7.03%7.48%7.51% 7.03% 8.0% 7.05% 61.67% 61.57% 6.50% 6.80% 6.70% 6.80% 6.70% 60.00% 7.0% 5.69% 5.30% 5.60% 5.60% 5.30% 5.40% 48.87% 48.47% 6.0% 36.62% 3.68% 40.00% 5.0% 3.68% 3.80% 4.06% 32.72% 32.72% 3.60% 36.32% 27.12% 32.99% 32.99% 3.63% 4.0% 3.07% 19.64% 2.30% 2.00% 2.23% 27.30% 3.0% 1.78% 1.78% 1.55% 1.70% 1.50% 20.00% 12.61% 19.79% 2.0% 7.31% 0.89% 0.89% 0.81% 12.74% 0.53% 0.47% 0.47% 0.26% 0.30% 0.30% 0.21% 0.19% 0.19% 1.0% 0.00% 0.00% 0.00% 0.00% 0.00% 3.63% 8.68% 1.85% 4.88% 0.96% 1.81% 0.49% 1.00% 0.19% 0.47% 0.00% 0.26% 0.00% 0.0%
2.00%
1.70%
1.50%
98.50%
100.00%
0.02%
Strictly Confidential
Monthly project progress update
UNIT#2 STEAM BLOW OUT
Strictly Confidential
Monthly project progress update
Turbine Area #02
Strictly Confidential
Monthly project progress update
CONDUIT INSTALLATION IN UNIT #03 HRSG
Strictly Confidential
Monthly project progress update
Turbine Area #02
Strictly Confidential
Monthly project progress update
MCT Installation in Turbine #02 Area
Vibration Sensor JB in Turbine Area
Strictly Confidential
Monthly project progress update
SPEED SENSOR INSTALLATION IN TURBINE AREA
LEVEL SENSOR IN DRUM TANK
Strictly Confidential
Monthly project progress update
INSTRUMENT INSTALLATION IN UNIT 2 TURBINE BUILDING
Strictly Confidential
AGENDA AGENDA
1. Project Introduction 2. HSE Improvement Plan & Key Highlights 3. QA/QC Improvement Plan & Key Highlights 4. Monthly Project Progress Update 5. Resource Planning 6. Post Covid’19 Challenges 7. SMART Construction & HILTI Update 8. New Ideas /System 9. Project Finance Status 10.Satellite Support Team 11.Save & Share Implementation
Resource planning Description Foreman Technician E&I Fitter Electrician Welder Labour/Scaffolder Subtotal-Direct Site Manager Project Control Engineer Project Engineer Planning Engg Quantity Surveyor Safety Supervisor QA/QC Engineer QA/QC Inspector Material Control Store Keeper Admin Assistant Crane/Lorry Operator Document Controller Construction Superindent Supervisor Site Engineer Permit Coordinator/Scaffolding Driver
Subtotal-Indirect
Total
Plan 7 21 12 11 3 35 89
Jan-21 Actual 6 21 11 10 3 33 84
Plan 4 10 7 7 2 24 54
Feb-21 Actual 4 10 6 8 2 24 54
Plan 3 10 5 5 1 22 46
1 1 1 1
1 1 1 1
1 1 0 1
1 1 0 1
1 1
3 1 2 1 0 1 1 1 0 2 2 1 2
3 1 2 1
2 1 2 1
2 1 2 1
1 1 1 1
1 1 1
1 1 1 0 1 1 1 1
1 0 1 0 1 1 1 1
1 1 1
2 2 1 2
Mar-21 Actual
0
1
1 1 0 1
21
21
16
15
13
0
110
105
70
69
59
0
Strictly Confidential
Resource planning MANPOWER DEMOB PLAN Sl.No Nationality
Description
Qty
Remarks
1
Malaysian
End of Contract(EOC)
16
2
Indian
Home Leave
12
3
Indian
Transfer to Thailand
13
4
Indian
Transfer to Singapore
4
Batch 5, Visa Under Progress
5
Indian
Transfer to Singapore
8
After Finish Project
6
Indonesian
End of Contract(EOC)
5
Send Back to Home country
7
Bangaladeshi
End of Contract(EOC)
1
Send Back to Home country
Total
59 Strictly Confidential
AGENDA AGENDA 1. Project Introduction 2. HSE Improvement Plan & Key Highlights 3. QA/QC Improvement Plan & Key Highlights 4. Monthly Project Progress Update 5. Resource Planning 6. Post Covid’19 Challenges 7. SMART Construction & HILTI Update 8. New Ideas /System 9. Project Finance Status 10.Satellite Support Team 11.Save & Share Implementation
Post Covid’19 Challenges
Frequent Changes on the SOP(Safety Operation Regulation) scope from HEM ( Based on the SOP regulation). As per Malaysian government announcement all the foreign workers must undergo the Covid’19 Screening test(PCR Swap test) starting form Jan 2021.
Strictly Confidential
Post Covid’19 Challenges
PCR TEST
Strictly Confidential
SHARING OF COVID’19 VACCINATION COVID19 VACCINATION PROGRAM IN MALAYSIA PHASES OF VACCINATION PROGRAM
Strictly Confidential
AGENDA AGENDA 1. Project Introduction 2. HSE Improvement Plan & Key Highlights 3. QA/QC Improvement Plan & Key Highlights 4. Monthly Project Progress Update 5. Resource Planning 6. Post Covid’19 Challenges 7. SMART Construction & HILTI Update 8. New Ideas /System 9. Project Finance Status 10.Satellite Support Team 11.Save & Share Implementation
SMART Construction & HILTI Update OVERALL CABLE WAY UPDATING PROGRESS(WEEKLY MONITOR)
Target Mhr
Actual Mhr
468
584 341 551 530 509
-11 -43 26-DEC-20
44
19-DEC-20
63
12-DEC-20
24
31-DEC-20
384
5-DEC-20
-137
319 171 73 95
28-NOV-20
419 310 96 84
48
639
21-NOV-20
-26
392
14-NOV-20
221
71
599
7-NOV-20
487 381
282
31-OCT-20
59
406
355
3-OCT-20
-53 29-AUG-20
14 22-AUG-20
-5 15-AUG-20
8-AUG-20
1-AUG-20
-85-102-106 25-JUL-20
-68
18-JUL-20
27
25 11-JUL-20
-400
144 4-JUL-20
-200
635 453 354
200 84 0
639
576 593 553 573
563
535
24-OCT-20
710 718
683 575
512
26-SEP-20
400
586 855
598
592
706
17-OCT-20
786 492
600
810
705 732
19-SEP-20
800
999
12-SEP-20
1000
1051 1269 1197 928 1119 1013 684 676
5-SEP-20
1200
1222
10-OCT-20
1400
Cable Way System Net Manhours Gain/loss - 01 July 2020 to 31 Dec 2020 1296
Mhrs Loss Strictly Confidential
0 10584 10805
26-SEP-20
3-OCT-20 Cum Actual
16601 16985
26-DEC-20 31-DEC-20
16017
15508
14978
17827
17486
16913
16361
15768
15192
14382
13818
13426
12743
12337
Cable Way System Cummulative Target Mhrs vs Actual Mhrs - 01 July 2020 to 31 Dec 2020
19-DEC-20
12-DEC-20
5-DEC-20
14427
13788
21-NOV-20 28-NOV-20
13320
14-NOV-20
12402
31-OCT-20
13001
12092
24-OCT-20
12055
11520
11165
10590
18000
7-NOV-20
11673
17-OCT-20
10-OCT-20
14000
9884
16000
11186
9949
9372
8373
19-SEP-20
8641
7787
7055
6350
9496
Cum Target Mhr 12-SEP-20
5-SEP-20
8002
7284
6574
5857
5173
12000
29-AUG-20
22-AUG-20
15-AUG-20
5976
5190
10000
8-AUG-20
1-AUG-20
4245
8000
4177
2949
20000
25-JUL-20
18-JUL-202908
1898
6000
11-JUL-20 1789
2000 676
4000
4-JUL-20 592
SMART Construction & HILTI Update
OVERALL CABLE WAY UPDATING PROGRESS(CUMMULATIVE MONITOR)
Strictly Confidential
SMART Construction & HILTI Update OVERALL PI FOR CABLE WAYS FOR MONTH OF JULY, AUG,SEPT,OCT,NOV & DEC CABLE WAY PI (QTY/MHR) JULY, AUG, SEPT,OCT,NOV & DEC
Difference 2.36% Actual PI 50.00%
Target PI
Target PI 47.64%
Actual PI
Target PI Actual PI Difference Total Qty(M) Target Mhr Actual Mhr Diff. Mhr
0.81 0.85 0.04 12,14,449 17,827 16,985 842
Difference Strictly Confidential
SMART Construction & HILTI Update OVERALL CABLE PULLING UPDATING PROGRESS(WEEKLY MONITOR)
Cable Pulling System Net Manhours Gain/loss - 01 July 2020 to 31 Dec 2020
7000 6000
6073
5750
5000
4046
4040
4000
3179
37963749 3377 3096 2373 2277 2000 3000
Target Mhr
Actual Mhr
31-DEC-20
26-DEC-20
19-DEC-20
12-DEC-20
5-DEC-20
28-NOV-20
21-NOV-20
14-NOV-20
7-NOV-20
31-OCT-20
24-OCT-20
17-OCT-20
10-OCT-20
3-OCT-20
26-SEP-20
19-SEP-20
12-SEP-20
5-SEP-20
29-AUG-20
22-AUG-20
15-AUG-20
8-AUG-20
11-JUL-20
-2000
4-JUL-20
-1000
25-JUL-20
291
0
1547 1473 1281 1064101211171191 10122109935 791 956 914 783 16761544 294 357 425 182 1300 0 1318126013891353 936 926 894 902 62 12 56 728 644 9 27 764 -88-114 -87 -162 444 539 -203 -246 -254-248-272 -263-288 -350 269 -562 -599 -671 -936 -1086 1-AUG-20
950
18-JUL-20
1000
1625 1116 67117871871 1217196219461757 1347
Mhrs Loss Strictly Confidential
5000
0
Cum Target Mhr 10-OCT-20
36226 37152 37916 38810 39712 40440 41083 41527 42066 42335
7-NOV-20 14-NOV-20 21-NOV-20 28-NOV-20 5-DEC-20 12-DEC-20 19-DEC-20 26-DEC-20 31-DEC-20
34117
24-OCT-20
Cable Pulling System Cummulative Target Mhrs vs Actual Mhrs - 01 July 2020 to 31 Dec 2020 43180
42998
42573
42217
41923
41140
40226
39270
38479
37544
35997
34985
33704
32231
31-OCT-20
32817
Cum Actual
17-OCT-20
31273
29597
31040
29923
28911
27847
27847
26222
25106
24435
45000
3-OCT-20
28244
26855
19-SEP-20
26-SEP-20
25595
24277
12-SEP-20
5-SEP-20
23341
21470
19683
17926
23088
40000
29-AUG-20
22-AUG-20
15-AUG-20
8-AUG-20
15980
19909
35000
1-AUG-20
14018
30000
25-JUL-20
15869
25000
18-JUL-2010269
20000
9796
50000
11-JUL-20 6473
10000 5750
15000
4-JUL-20 3377
SMART Construction & HILTI Update
OVERALL CABLE PULLING UPDATING PROGRESS(CUMMULATIVE MONITOR)
Strictly Confidential
SMART Construction & HILTI Update OVERALL PI FOR CABLE PULLING FOR MONTH OF JULY, AUG,SEPT,OCT, NOV & DEC CABLE PULLING PI (QTY/MHR) JULY, AUG, SEPT,OCT, NOV & DEC
Difference 0.98% Actual PI 50.00%
Target PI
Target PI 3.80 Actual PI 3.88 Difference 0.08 Total Qty(M) 164,194 Target Mhr 43,180 Actual Mhr 42,335 Diff. Mhr 845
Target PI 49.02%
Actual PI
Difference Strictly Confidential
SMART Construction & HILTI Update EQUIPMENT MONITOR
Strictly Confidential
SMART Construction & HILTI Update EQUIPMENT MONITOR
Strictly Confidential
SMART Construction & HILTI Update EQUIPMENT MONITOR
MMCC Project HILTI TRACKING STATUS
Strictly Confidential
AGENDA AGENDA 1. Project Introduction 2. HSE Improvement Plan & Key Highlights 3. QA/QC Improvement Plan & Key Highlights 4. Monthly Project Progress Update 5. Resource Planning 6. Post Covid’19 Challenges 7. SMART Construction & HILTI Update 8. New Ideas /System 9. Project Finance Status 10.Satellite Support Team 11.Save & Share Implementation
NEW IDEAS SYSTEM
Fibre Optic Splicing works & Related testing Plan to establish in Other BU’s/Overseas. FO TERMINATION ENQUIRY FROM OVERSEAS PROJECTS (SINGAPORE, THAILAND & INDONESIA)
SUPERMEC
ROTARYMEC Strictly Confidential
NEW IDEAS SYSTEM
FIBRE OPTIC TERIMANATION
Strictly Confidential
NEW IDEAS SYSTEM
FIBRE OPTIC TERIMANATION
Strictly Confidential
AGENDA AGENDA 1. Project Introduction 2. HSE Improvement Plan & Key Highlights 3. QA/QC Improvement Plan & Key Highlights 4. Monthly Project Progress Update 5. Resource Planning 6. Post Covid’19 Challenges 7. SMART Construction & HILTI Update 8. New Ideas /System 9. Project Finance Status 10.Satellite Support Team 11.Save & Share Implementation
PROJECT FINANACE STATUS BASE CONTRACT VALUE
: RM 16,000,000
Amended REV.1 CONTRACT VALUE
: RM 20,070,000
(Incl. VO Job) TOTAL INVOICE : RM 17,519,803.42
JAN MONTH INVOICE : RM 1, 001,805.00
(As of Jan 2021)
INVOICED VALUE
CASH OUT
17,519,803.42
RM 16,977,628.52
Note: • Cash flow details until 31/Jan/2021
MMCC Project MMCC Project Cash Flow Cash Flow Forecast Updated Updated Jan'20 Strictly Confidential
AGENDA AGENDA 1. Project Introduction 2. HSE Improvement Plan & Key Highlights 3. QA/QC Improvement Plan & Key Highlights 4. Monthly Project Progress Update 5. Resource Planning 6. Post Covid’19 Challenges 7. SMART Construction & HILTI Update 8. New Ideas /System 9. Project Finance Status 10.Satellite Support Team 11.Save & Share Implementation
SATELLITE SUPPORT TEAM
Currently doing satellite support team (from MMCC) arrangement for Thailand/Singapore project on following activity:
HR/Admin Support Transfer workers co-ordination with RMEC HQ/Thailand HR/Singapore HR submitting documents for Visa Processing.
Procurement Support Preparing Tools & Equipment’s list for project requirements.
Planning Support Preparing Project Schedule & Manpower planning schedule.
Strictly Confidential
AGENDA AGENDA 1. Project Introduction 2. HSE Improvement Plan & Key Highlights 3. QA/QC Improvement Plan & Key Highlights 4. Monthly Project Progress Update 5. Resource Planning 6. Post Covid’19 Challenges 7. SMART Construction & HILTI Update 8. New Ideas /System 9. Project Finance Status 10.Satellite Support Team 11.Save & Share Implementation
Save & Share Implementation
MMCC project sharing with Euro 05 Project details as below mentioned Lorry crane 15T and driver for demob equipment's to Mantin Warehouse. 40Ft Trailer and driver for demob Tools/Equipment's to Mantin Warehouse. Rigger for demob equipment’s and Lifting activities. Fibre Optic Equipment with trained person with Euro 05 Project for Fibre Optic Termination.